Assets

Customer Information

Disclosures
Accordion Arrow

Current disclosures

Date and Time of Disclosure: 23 May 2024 10:02 Hours | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 07 June 2024 06:00 Hours | Expected Day Back: 27 June 2024 06:00 Hours | Expected Availability: Zero availability of CATS Terminal and Pipeline

Previous (non-current) disclosures

Date and Time of Disclosure: 24 February 2023 12:18 Hours | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 24 February 2020 00:10 Hours | Expected Day Back: 24 February 2023 18:00 Hours | Expected Availability: Zero availability of CATS Terminal and Pipeline


Date and Time of Disclosure: 08 October 2020 16:30 Hours | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 08 October 2020 09:35 Hours | Expected Day Back: 08 October 2020 23:59 Hours | Expected Availability: Zero availability of CATS Terminal and Pipeline


Date and Time of Disclosure: 24 March 2020 13:00 Hours | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 26 March 2020 06:00 Hours | Expected Day Back: 27 March 2020 14:00-16:00 Hours | Expected Availability: Zero availability of CATS Terminal and Pipeline


Date and Time of Disclosure: 20 November 2018 | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 1 August 2019 | Expected Day Back: 10 August 2019 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 25 June 2016 | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 6 June 2016 | Expected Day Back: 26 June 2016 | Expected Availability: Zero availability of CATS Processing Plant


Date and Time of Disclosure: 25 June 2016 | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 6 June 2016 | Expected Day Back: 24 June 2016 | Expected Availability: Zero availability of CATS Pipeline and Reception Facilities


Date and Time of Disclosure: 31 March 2016 | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 6 June 2016 | Expected Day Back: 1 July 2016 | Expected Availability: Zero availability of CATS Terminal and Pipeline


Date and Time of Disclosure: 05 February 2016 | Operator: CATS North Sea Limited | Terminal: CATS | Expected Day Off: 6 June 2016 | Expected Day Back: 6 July 2016 | Expected Availability: Zero availability of CATS Terminal and Pipeline


Date and Time of Disclosure: 31 July 2015 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 June 2016 | Expected Day Back: 1 July 2016 | Expected Availability: Zero availability of CATS Terminal and Pipeline


Date and Time of Disclosure: 26 March 2015 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 8 December 2014 | Expected Day Back: 31 March 2015 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 26 February 2015 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 8 December 2014 | Expected Day Back: towards the end of March 2015 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 12 December 2014 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 8 December 2014 | Expected Day Back: not yet known | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 31 July 2014 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 November 2014 | Expected Day Back: 2 December 2014 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 31 July 2014 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 August 2014 | Expected Day Back: 15 August 2014 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 9 September 2013 10:22 | Reference: 2013/006 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 9 September 2013 | Expected Day Back: 10 September 2013 | Expected Availability: Zero availability of CATS Terminal and CATS Pipeline


Date and Time of Disclosure: 28 August 2013 18:20 | Reference: 2013/005 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 August 2013 | Expected Day Back: 28 August 2013 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 27 August 2013 17:48 | Reference: 2013/004 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 August 2013 | Expected Day Back: 27 August 2013 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 20 May 2013 16:00 | Reference: 2013/003 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 August 2013 | Expected Day Back: 26 August 2013 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 27 February 2013 17:00 | Reference: 2013/002 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 August 2013 | Expected Day Back: 15 September 2013 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 12 February 2013 11:50 | Reference: 2013/001 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 21 February 2013 | Expected Day Back: 23 February 2013 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 30 October 2012 17:50 | Reference: 2012/010 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 18 November 2012 | Expected Day Back: 19 November 2012 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 22 October 2012 16:50 | Reference: 2012/009 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 10 November 2012 | Expected Day Back: 11 November 2012 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 2 October 2012 19:00 | Reference: 2012/008 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 June 2016 | Expected Day Back: 1 July 2016 | Expected Availability: Zero availability of CATS Terminal and CATS Pipeline


Date and Time of Disclosure: 2 October 2012 19:00 | Reference: 2012/007 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 August 2015 | Expected Day Back: 2 August 2015 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 2 October 2012 19:00 | Reference: 2012/006 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 August 2014 | Expected Day Back: 2 August 2014 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 2 October 2012 19:00 | Reference: 2012/004 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 3 June 2013 | Expected Day Back: 28 June 2013 | Expected Availability: Zero availability of CATS Processing Terminal


Date and Time of Disclosure: 2 October 2012 19:00 | Reference: 2012/005 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 July 2013 | Expected Day Back: 15 August 2013 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 5 March 2012 17:10 | Reference: 2012/001 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 June 2016 | Expected Day Back: 21 June 2016 | Expected Availability: Zero availability of CATS Terminal and CATS Pipeline


Date and Time of Disclosure: 5 March 2012 17:10 | Reference: 2012/002 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 1 June 2013 | Expected Day Back: 24 June 2013 | Expected Availability: Zero availability of CATS Riser Platform


Date and Time of Disclosure: 5 March 2012 17:10 | Reference: 2012/003 | Operator: Amoco (U.K.) Exploration Company, LLC | Terminal: CATS | Expected Day Off: 3 June 2013 | Expected Day Back: 23 June 2013 | Expected Availability: Zero availability of CATS Processing Terminal and CATS Pipeline


Date and Time of Disclosure: 20 December 2011 19:00 | Reference: 2011/001 | Operator: Amoco (U.K.) Exploration Company | Terminal: CATS | Expected Day Off: 1 June 2013 | Expected Day Back: 21 June 2013 | Expected Availability: Zero availability of CATS Processing Terminal

Availability
Accordion Arrow

The availability record of CATS is exemplary, delivering an average annual availability over the past 10 years of (including planned and unplanned downtime):

The availability record for unplanned outages only, over the same period, is:

To further improve our availability to customers, CATS operates a non-intrusive inspection philosophy as part of a comprehensive Integrity Management Scheme.

We aspire to use this work to justify increasing the duration between shutdowns for visual inspection while continuing to maintain the plant to exacting standards and meeting our legal and regulatory obligations in this respect.

Entry Requirements
Accordion Arrow

The CATS pipeline has six subsea tees. Entry to the CATS system can be offered via a flanged entry point on one of the six subsea tees on the pipeline, at the CATS riser platform, or via one of the existing CATS hubs, subject to agreement with the hub owner.

Details of the typical gas entry specification and product specifications for CATS can be downloaded below:

Download Typical Gas Entry & Product Specifications


Legal & Regulatory

Prior to entry works commencing, all appropriate regulatory, HSE and legal requirements must be met. The minimum requirements are summarised as follows:

Regulatory

OGA Pipeline Works Authorisation for subsea pipeline tie-in design and installation will include all associated consents and permits, both for the new third-party pipeline connecting to the CATS pipeline and any agreed modifications to the CATS system:

  • Compliance with BS8010 subsea pipeline design and construction code requirements (or equivalent pipeline code e.g. DNV2000, subject to CATS approval)
  • Compliance with all other CATS requirements pertaining to the safety of construction operations on the CATS pipeline, or within the safety zone of the pipeline and other associated CATS infrastructure.

Legal

Agreement between all Shippers:

  • Cross User Liability Agreements, defining system user liabilities

Agreements between CATS Parties and individual Shippers:

  • Transportation Allocation Agreement
  • Processing Allocation Agreement
  • Cross Indemnity Deed

Agreements between CATS Parties and individual Shippers:

  • Transportation and Processing Agreement
  • Use of the CATS Riser Platform Agreement (if entering CATS at the CATS Riser Platform)
  • Engineering Services Agreement

Agreement between CATS Parties, Shippers and Host Platform Owners:

  • Shipper User Agreement
CATS System Technical Overview
Accordion Arrow

The CATS system carries natural gas from various points in the North Sea to the CATS terminal at Seal Sands, Teesside.

Natural gas delivered into the CATS system at the CATS system offshore riser platform (CRP) or other points of entry along the pipeline (the CATS pipeline) is redelivered to CATS system users at specified redelivery points located at the CATS terminal.

Further technical details on the CATS system can be downloaded here.

Download CATS System Technical Overview

View the CATS system animation on our Media page.

Standard Terms
Accordion Arrow

The CATS Standard Terms set indicative commercial terms on which CATS Parties are prepared to negotiate with the gas owners (shippers) for CATS to transport and process the gas – subject to approval from the respective boards of directors.

It is not intended to be an offer capable of acceptance or to create any legally binding arrangement or obligation.

Matters remain on a subject-to-contract basis unless and until legally binding agreements are executed.

Any discussions on these non-binding terms will be on the understanding that any negotiations and eventual agreement will need to satisfy all regulatory and legal requirements.

When agreed, these commercial terms will be embodied in a fully termed transportation and processing agreement.

CATS Parties may revise, update or replace any or all of the standard terms from time to time.

Additionally, the CATS System offers a number of key benefits to potential customers, including:

  • Excellent availability (average of 99.3% over the last five years)
  • Customer focus – the system offers attractive and competitive services to customers’ fields
  • Access to low NTS Entry Charge – attractive differential NTS charge between Teesside and St Fergus
  • Contaminants removal service available
  • Excellent safety and environmental record, including British Safety Council 5 Star Health and Safety Awards (seven years running) and the Tees Valley Business Environmental Award (2004)

The CATS Parties unanimously support the Infrastructure Code of Practice and the Commercial Code of Conduct and are committed to supporting the development of fields in the North Sea.

Prospective Shippers, who are interested in receiving terms and conditions specific to their development, should contact the CATS Commercial Team at: info@kellasmidstream.com

This application should provide information regarding the services requested, gas profiles, gas specification and amount of capacity required.

Following receipt of applications, providing the application is a bona fide request for provision of terms for transportation and processing services, and providing there is sufficient relevant information supplied, we would anticipate responding within 10 working days.

We welcome the opportunity to speak with all prospective customers.


Standard terms – transportation & processing

The CATS Standard Transportation and Processing Agreement is based around two key components:

(i) Section I - Form of Agreement (Specific Terms)

Each new field is different and sometimes requires an individual commercial solution depending on the nature of service required. We have grouped together the key commercial terms, that may vary from field to field, into a simple streamlined document that can be negotiated and drafted simply and quickly.

(ii) Section II - Conditions of Contract (General Terms)

The CATS System is a large integrated gas transportation and processing system which offers its transportation and/or processing services to a number of Shippers. Based on our experience and our varying commitments, this agreement details the general terms, conditions and procedures, applicable to all shippers, that have been developed over time to ensure the safe, efficient and sustainable operation and management of the CATS System. A copy of the CATS Standard Section II – Conditions of Contract for the Transportation and Processing Agreement can be downloaded below.

Download CATS Standard II Conditions of Contract for the Transportation & Processing Agreement


Standard terms – processing

Indicative Terms and Conditions for the processing of gas by CATS are available by contacting Kellas Midstream Limited.


Standard terms – small fields

The CATS Partners have developed indicative Small Fields terms, including no send or pay and a flexible capacity booking mechanism to enable prospective customers with small gas volumes to access the UK gas market through the CATS System.

These terms have been designed specifically to meet the needs of new developments with total reserves of less than 50 mmboe and gas reserves of less than 10 mmboe. They are available for new customers seeking a transportation and processing service and entering CATS via any of the CATS Ts, the CATS Riser Platform or via an existing hub platform (subject to the necessary agreements with the appropriate field owners).

CONTACT US

Kellas Midstream Limited

6th Floor, The Capitol
431 Union St
Aberdeen
AB11 6DA

Tel: +44 (0) 1224 084520


Pipeline Emergency

To report a pipeline emergency please call +44 (0)1642 546404 and ask for the Operations team.